LKAB WGC Plant

Customer: Outotec GmbH
Location: Malmberget, Sweden
Project manager: Mikk Helleste

Description

Maru Metall signed an agreement with Outotec GmbH on January 2nd 2013 to design and produce steel frames for gas treatment plant built on LKAB territory. The contract covers the production of approximately 750 t of steel structures, in addition ladders, stainless steel handrails, grilles, steps, etc.

Work is carried out by Maru Metall AS

Maru Metall AS

Järvevana tee 5,
10132 Tallinn, Estonia
Phone: +372 650 8820
Fax: +372 650 8821
E-mail: metall@marurakennus.fi